Alaska Approves 50-Year Lease for Gas-Powered North Slope Data Center

Alaska's Department of Natural Resources approved a 50-year land lease on Tuesday, 10 November, for a data center on the North Slope that would make its own electricity from local gas. The STAK Energy Campus is planned on about 715 acres near Prudhoe Bay, close to the Dalton Highway and the trans-Alaska oil pipeline and 60 miles from the nearest inhabited town. The Alaska Beacon's James Brooks reported the decision in the Anchorage Daily News. The department found the lease to be in the state's best interest. Alaska has no large commercial data center today.

Its own power plant, no line to the Railbelt

The complex would include a natural gas power plant of 1 to 3 GW, fired with gas produced on the North Slope. It would not be connected to the Railbelt grid that serves most Alaskans, although the operators could sell electricity to customers in and around Prudhoe Bay. Initial site development is put at $500 million, privately financed. Construction is expected to take six years, according to information given to the department, with up to 1,500 workers at the peak and 50 to 150 permanent staff on rotating shifts afterwards.

The computer buildings are modular and air-cooled. They are to stand above a gravel pad so that arctic air can pass over and under them. The department cites STAK's own impact analysis, which estimates direct water consumption in operation at least 90 percent lower than at an evaporatively cooled data center further south.

The department explains the 50-year term with the capital the project needs: STAK has to be able to recover its investment over the useful life of the plant. The state will charge rent for the land and a fee based on the electricity the campus generates and uses, both to be set by market appraisal. The report gives no amounts.

More than 1,200 comments, most against

The comment period was extended earlier this year and brought more than 1,200 responses, most of them opposed. The department answered them in a 30-page document filed with the approval. Three of its answers:

  • Whether STAK can finance and build the project is outside the department's purview, and it is not required to carry out a general financial investigation of the company.
  • On noise, the department writes that the facility will be visible from the Dalton Highway at about one mile and that sound from turbines, cooling and other equipment could carry for several miles across the flat terrain. It weighs this against the site's position in the industrial corridor that serves the Prudhoe Bay oil fields.
  • On greenhouse gases from the power plant, it says it is not the agency that sets or enforces such standards.

The buildings and the gas pipeline that supplies the plant are to be designed so that they do not affect nearby caribou. The Anchorage Daily News adds that John Boyle, a former commissioner of the department, is now STAK Energy's chief strategy officer.

What is still open

A lease is not a permit to build. The decision can be reconsidered within 20 days and can be challenged in court. After that the project needs a federal wetlands permit and a state air quality permit for the power plant, and other agencies will ask for baseline studies first, among them air quality monitoring at the site, wetland delineations and water quality assessments.

For the generating plant, the sentence about the Railbelt is the one that sets the brief. With no grid behind it, there is no standby duty here in the usual sense. The units run as the only source, and the spare capacity for maintenance and for a tripped machine has to stand on the same pad. In that climate an enclosure has two opposite jobs - getting the heat out of a machine at full load, and keeping a stopped one warm enough to start, which is where pre-heating comes in. The air permit will show how many units are planned and of what kind; the lease decision, as reported, does not.

Sources: Anchorage Daily News / Alaska Beacon