The largest data center yet proposed in Alabama has an operator. On 4 November the AI cloud company Lambda said it is the end user of the Red Clay Technology Center Campus in Lowndes County, near the junction of U.S. Highway 80 and Alabama Highway 21, and put the investment at an estimated $33.1 billion. The site has been prepared by the developer Cloverleaf Infrastructure, whose chief executive David Berry confirmed Lambda as the user. Alabama Power is to supply the electricity, subject to regulatory approval.
1,500 MW six miles from Montgomery
Lambda's own release gives no capacity figure. The Alabama Political Reporter describes the project as a 1,500 MW campus on about 2,200 acres in the north-east of the county, roughly six miles south-west of Montgomery. Construction is planned to begin in the first quarter of 2027 and to take up to five years, with more than 1,000 construction jobs over that period and more than 225 permanent positions once it runs.
The buildings will use closed-loop cooling, which Lambda says needs much less water than conventional systems, and the company plans to work with N-Drip on water saving for local farmers. The project has asked for 100,000 gallons of water a day; Cloverleaf told the paper this is needed during construction and that daily use will fall a long way once the campus is finished. Setbacks, buffers, noise reduction and DarkSky lighting are listed among the commitments to neighbours, together with a $10 million community benefits agreement.
Who pays for the grid connection
Lambda says it will make upfront financial commitments that cover the full cost of the power supply and the grid infrastructure for the campus, binding even if its plans change, so that existing Alabama Power customers do not carry them. Both Lambda and the utility have signed the White House Ratepayer Protection Pledge. The companies project more than $2.8 billion of local tax revenue through 2049, more than $1.6 billion of it for the county's schools.
Two lawsuits over the tax break
Not everyone in the county is convinced. On 13 October the county commission voted 3-2 to approve more than $2.7 billion in local and state tax abatements for the project. Residents filed a first lawsuit in October over the notice given for that meeting. This week a second followed, brought by the group Protect Lowndes County and the Alabama Rivers Alliance with lawyers from the Southern Environmental Law Center and the Natural Resources Defense Council. It claims breaches of the state's Open Meetings and Open Records Acts: residents had been told the abatements would come up on 20 October, a week after the vote, and records about the project were not released. The plaintiffs want the tax breaks set aside. The commission's counsel had not commented by the time of the report.
Nothing published so far says how the campus will be backed up, and for a site fed by one utility at this scale that is the next file to watch. Standby plant for 1,500 MW means a long list of engines, an air permit that has to state their hours and a fuel store that has to be kept fit to burn, if necessary with fuel polishing. On a project that has already reached the courts over a meeting notice, expect the generator permit and the noise at the boundary to be read line by line. With a five-year build, the first sets are likely to be ordered well before the last buildings are designed, at the lead times Generac described last month.
Sources: Lambda, Alabama Political Reporter, Alabama Political Reporter (lawsuit)