Google's 250 MW San Jose Site May Be Approved Before New Rules

Google's project on Disk Drive in Alviso, North San Jose, could be approved before the city has finished its rules for data centers. San José Spotlight reported this week that the 250 MW development may come before a Planning Director's Hearing as early as December. The City Council is expected to vote on its data center development standards in the same month, and projects approved before those standards are final would not have to meet them.

An R&D lab with generator yards

Google describes the site as research and development. The plan is to clear a warehouse and its parking lot and build up to three facilities with close to 483,000 square feet. According to the report, the drawings show an on-site substation and switching station with three transformers, several generator yards and cooling stations. The city files it as a large energy use project; the California Public Utilities Commission (CPUC) refers to it as a data center.

The approval route is short. A hearing officer presides, the decision only goes to the Planning Commission if someone appeals, and the city relies on environmental reports from 2000 and 2013 instead of a new full review under CEQA. A city spokesperson said the environmental document will be published before any hearing and that no date has been set.

The power side goes to the CPUC on 19 November

  • CPUC staff recommend approving an agreement to serve the site, under which Google advances $150 million for transmission and grid upgrades.
  • The advance would be paid back to Google in full over 15 years through rates paid by all customers.
  • Google also needs CPUC approval to operate; the decision has been delayed since summer and is on the agenda for 19 November.

What the pending standards say about generators

The draft standards, in the version cited by San José Spotlight, require diesel backup generators to meet the strictest federal emission standards and to run only during power outages. Operators would report their water and electricity use each year and face an independent audit every five years. Councilmember David Cohen, whose district includes the site, said he expects any approved project to meet whatever the council adopts. Local advocates see a rush; the city lists 16 data centers and large energy use projects approved or in the pipeline.

The generator question here is a matter of timing. A project consented under the old rules keeps them, so the difference shows in the air permit and the test regime rather than in the planning file. We covered the details of the draft, including its limit on test hours, when it was published. Whoever buys the gensets for those generator yards will want to know which version applies before the order is placed, not after.

Sources: San José Spotlight, CPUC voting meeting, 19 November 2026