Luzerne County Narrows After-Hours Generator Use at Data Centers

Which data center is "essential"? In Luzerne County, Pennsylvania, the answer now decides whether a facility may run its emergency generators in the evening and at night. On Thursday, 12 November, the county Planning Commission approved a definition of that one word for its proposed data center zoning ordinance and recommended the amended text to County Council, the Times Leader reports.

The word the first draft left open

As the paper describes the draft, generators can be operated between 5 p.m. and 8 a.m. only under two conditions. One is an emergency declared by county emergency management, by state or federal authorities, or by a grid or utility operator with the authority to do so. The other is that the facility has been deemed essential.

What the earlier version did not say is what makes a facility essential. Ted Ritsick, head of the county's Community Planning and Economic Development Division, said the omission came to light in a discussion with County Councilwoman Denise Williams.

Defense, public safety, hospitals, government

The definition the commission approved ties the classification to the function the generator protects, not to the building:

  • The generator must be necessary for the continued operation, security, continuity or recovery of a function directly related to national defense or security, public safety or emergency response, inpatient or emergency medical care, or the continuity of government operations.
  • Losing that function, or a material interruption of it, must pose a direct and substantial risk to human life, public safety, national security or national defense.
  • The applicant has to bring documentation from a government agency, a military department, a healthcare institution, a public utility or another responsible body which shows that the function is needed for that body's continuity, security, resiliency or operation.
  • The zoning officer decides, in consultation with the county Department of Emergency Services.

Ritsick gave an example. Data that a hospital needs to save lives when the power fails would be protected. A data center that handles entertainment or other non-essential information would not be allowed to put the noise of a running generator on its neighbours after hours.

Nineteen municipalities and no applicant

The ordinance would apply in the 19 municipalities that rely on county zoning and have none of their own, twelve boroughs and seven townships. It also requires a special exception approval from the county Zoning Hearing Board for every data center request, with a long list of conditions that the report does not go through. According to Ritsick, no application and no credible proposal for a data center has been submitted in these municipalities so far.

The three commission members present, led by Chairman Salvatore A. Marsico, approved the changes. County Council has the final say. It is to hold the hearing required by the Pennsylvania Municipalities Planning Code on 8 December, its last scheduled meeting of the year, and could introduce the ordinance the same evening. Council Chairman Jimmy Sabatino has not decided whether to call a special meeting later in December or to leave the second hearing and the adoption vote to 12 January.

Two things to ask the zoning officer

The report says nothing about test runs. A standby set has to be started and loaded at regular intervals whether or not the grid ever fails, and most operators can do that in daytime. Whether the ordinance treats testing separately from emergency running is the first passage we would look for in the full text.

The second point concerns the commercial operator. As reported, a colocation or cloud site that cannot show a defense, public safety, medical or government function would depend on somebody else declaring an emergency before its generators may run after 5 p.m. That is a matter for the lender and the insurer as much as for the engineer, and it is better raised before the land is bought. Next door in Lackawanna County, Archbald turned down a campus with 588 diesel generators outright. Luzerne is taking the other road and writing the conditions down first, and for the sites that do qualify, the noise of a night run will still be measured against the enclosures and the inlet and outlet silencers that were bought.

Sources: Times Leader