Consumer advocates from seven PJM states have joined the grid operator's own market monitor in asking for the next capacity auction to be postponed. In a letter to the PJM board on 18 November they asked that the base residual auction for the 2029/30 delivery year, scheduled for 9 to 15 December, wait until data center load, real and speculative, can be taken out of the load forecast and until PJM has held a separate reliability backstop procurement for large loads, Utility Dive reported the next day.
Who signed and what they want
The signatories are the Ohio Consumers' Counsel, the Delaware Public Advocate, the West Virginia Consumer Advocate, Maryland's Office of People's Counsel, Pennsylvania's Office of Consumer Advocate, New Jersey's Division of Rate Counsel, the Illinois Attorney General's Office and the Illinois Citizens Utility Board. They asked the board for a written answer by 23 November. Any delay would need FERC approval.
The case rests on the market monitor's report of 12 November. Monitoring Analytics warned that PJM's forecast still contains data centers that have been cancelled or are unlikely to reach their projected demand, which could add $5 billion to $10 billion in costs for PJM's 67 million consumers. The same report puts the capacity cost increase from existing and forecast data center demand at $29.4 billion for all customers.
A cleaned-up forecast is not enough for the advocates. They want forecast data center demand treated separately in the auction, so that existing customers do not pay for load that may never arrive, and they point to a January statement of principles, endorsed by PJM and the governors of its 13 states, that large-load forecasts must be real and verified.
PJM is not inclined to wait. Spokesman Jeffrey Shields told Utility Dive that the auction already has a price cap as a safeguard, that the system urgently needs capacity, and that postponing so close to the date could unsettle the market and raise the risk of supply interruptions. PJM has to plan for the demand that policymakers and utilities allow to connect, he said. PJM was also due to publish its final planning parameters on 19 November, which may take cancelled or delayed data center projects out of the demand curve. Exelon has had a complaint at FERC since 3 November challenging the three-year forward auction, partly over the same forecast uncertainty.
Why a generator buyer should care about an auction
The argument over who carries data center capacity costs ends up in tariffs, and tariffs decide how much a site wants to stand on its own feet at peak. PJM's two-part answer to the shortage, as Utility Dive describes it, is bilateral contracts outside the auctions plus a backstop procurement for large loads that have no such contract. Both are still pending.
In our reading, a data center that brings its own capacity, or can show that it will curtail onto on-site plant, sits better in either track than one that simply waits in the queue. That has been the direction since FERC turned down PJM's curtail-first plan, and this letter does not change it.
Sources: Utility Dive