Utilities Plan Under a Third Carbon-Free Supply for Data Center Load

How much of the power promised to US data centers will actually come from clean plant? Less than a third, on the utilities' own plans. Latitude Intelligence, the research arm of Latitude Media, published a first look at its "Terms of Power II" study on 10 November. If every carbon-free project these utilities have proposed is built, it covers about 30% of the electricity their signed data center customers will need. Counting only projects that regulators have approved, the share drops to 15%.

Contracted, signed, and the rest

The study starts by separating reported demand from load under contract. Across the utilities it tracks there is about 500 GW of reported data center demand and 122.9 GW under contract; at a typical utility only 9% of reported load sits under an agreement that commits the customer to take the power. Just over half of the utilities have signed less than a tenth of their reported data center load, and almost a quarter have signed none. Some examples from the article: Georgia Power has 12.8 GW signed out of an 80.1 GW large-load pipeline, AEP Ohio 26.9 GW under service agreements, and Dominion Energy reported 54.9 GW of contracted capacity on 30 October, of which 12.2 GW is under electric service agreements.

For the signed load, new gas is the biggest single supplier in the resource plans of the vertically integrated utilities. The 69 GW of gas plant planned or under construction would cover about 45% of the energy those data centers need, assuming they draw 65% of their contracted capacity. About 120 TWh a year, roughly a quarter, has no planned supply at all, and at a 90% draw the gap could reach about 225 TWh.

73.7 GW behind the fence

The figure that matters most for our side of the business sits further down: data center customers plan to bring 73.7 GW of their own generation, almost all of it gas, according to the analysis. The article gives no split between engines, turbines and fuel cells.

Two more points from the study explain why. Some 63 GW of solar, wind and batteries in the utility plans has not yet gone out to bid, including most of what is due by 2030. And 59% of the signed load is in states that do not require utilities to add carbon-free power at all.

Read together, the numbers say that a large part of the new load will lean on gas whichever side of the meter it is on, and that the utility supply behind a signed contract may still be on paper. For projects with their own plant, that means emissions permits for continuous operation rather than emergency hours, gas supply agreements and maintenance planned like a power station's. The standby fleet does not go away either; it now sits next to a prime power plant. Latitude notes that PJM intends to file rules this month for data centers that bring their own power, a subject we followed in Google's Constellation deal.

Sources: Latitude Media, Latitude Intelligence, The Terms of Power II