About 40% of Planned US Data Center Capacity Faces Governor Pauses

Until now the first question on a US data center site was where the power would come from. After this month's elections there is a second one. Data from the market intelligence firm Cleanview, reported by Bloomberg on 6 November, show that about 40% of the data center capacity planned in the United States lies in states whose newly elected governors have promised to stop or pause construction. The National, working from the same Cleanview data with its own list of states, arrives at 37%.

State by state

  • Ohio: Governor-elect Amy Acton takes office in January. According to Bloomberg she can halt state permitting for data centers by executive order and tighten oversight through appointments, including to the utility commission; permanent changes, such as extending the freeze on the tax credit, need the legislature.
  • Texas: Gina Hinojosa promised a moratorium and more say for communities on where data centers go, The National reports. In its count Texas holds 22.8% of planned US capacity.
  • Georgia: Keisha Lance Bottoms has pledged a pause on large data centers.
  • Michigan and New Mexico: the incoming governors campaigned on stopping or pausing them; in New York and Oregon the governors want to extend pauses already in force.
  • Iowa and Nevada: the incoming governors want to end tax breaks for AI data centers.
  • Florida: Byron Donalds, the next governor, has promised a measure that would require data centers to produce their own electricity instead of drawing it from the grid.

Governors appoint the regulators who set electricity prices and grid connection terms, and they have a say over state tax incentives. Zoning and property taxes, however, stay with cities and townships, which is why Joshua Basseches of Case Western Reserve University told Bloomberg that local ballot measures act faster. Bloomberg Economics counts 46 local measures approved or on track to pass, at least 17 of them outright bans on large data centers.

Where the projects go next

Justin Teresi of Bloomberg Intelligence said the question has moved from who will pass a moratorium to where a developer can still build. Gordon Johnson of GLJ Research expects Texas projects that do not yet have their power and environmental permits to go to Louisiana or Oklahoma, or nowhere. Dan Diorio of the Data Center Coalition said the investment will go to communities and states that stay open. Bloomberg Intelligence analyst Mandeep Singh estimates that the $1.4 trillion of AI infrastructure spending expected for 2027 could shrink by about 5% to 7%, and that up to 10 GW may not come online next year as planned. OpenAI, for its part, said it will avoid nondisclosure agreements in data center deals and make sure residents do not pay for the electricity its projects use.

Two items on that list matter directly to the generator side of the business. A halt on state permitting reaches the air permits that every standby fleet needs, so sets already ordered for a site in a pausing state may wait in a yard or follow the project across a state line, with a new permit application at the other end. The Florida idea, if it becomes law, would turn the standby plant into the main plant, with engines permitted for continuous running and a fuel supply to match. The local version of this fight showed up in the local ballot results earlier this month; at state level it is new.

Sources: Bloomberg (via Insurance Journal), Energy Connects, The National