Florida's new law on who pays for data center power has had its first test, and the utility did not pass it. On 3 November the Florida Public Service Commission voted 5-0 against the large-load tariff that Duke Energy Florida had proposed for data centers and other very large customers. Duke now has to file a new proposal.
What SB 484 asks for
The law, SB 484, was signed by Governor Ron DeSantis in May. It requires utilities to set tariffs and service conditions that reasonably ensure each large-load customer, a hyperscale data center for instance, bears its own full cost of service, including the connection and the added transmission and generation, and that neither those costs nor the risk of non-payment are passed on to other ratepayers. WUSF notes that the law also strengthens the right of cities and counties to turn data centers away.
Duke was the first investor-owned utility to file a compliance proposal. Utility Dive, reporting from the hearing in August, described a filing with a minimum service term of 20 years and a change to the construction contribution tariff, so that large-load applicants would pay the full estimated cost of extending service in advance. A new rate for large loads was not part of it. Duke argued that its existing protections were enough and pointed to its rate settlement, which runs to the end of 2027. Public Counsel Walt Trierweiler replied that the settlement gives no exemption from the statute.
Where the commission found gaps
PSC staff had recommended a denial in late October. The commission found that Duke's tariff left out some customers who fall under the law's definition of a large load, and that the utility had not shown enough evidence that its existing rate schedules, together with the contractual and financial protections it offered, would recover the full cost. Chair Gabriella Passidomo Smith said Duke can still serve large data centers while following the law. A Duke spokesperson said the company appreciated the commission's review and wants data centers to pay their full cost of service.
On paper this is a tariff case. In practice, every rule that puts the full cost of a grid connection on the large customer, with long minimum terms and money paid up front, moves a developer's numbers toward a smaller connection and more generation on its own land, and toward a standby plant that may be asked to do more than ride through outages. Each project makes that calculation for itself, and in Florida it now waits for Duke's second filing. Whatever the tariff becomes, the generators still need their air permit, their test schedule and somewhere to keep the fuel, whether in a separate store or a belly tank under each set.
Sources: WUSF (News Service of Florida), The Bradenton Times (Florida Phoenix), Utility Dive