PPL Corporation reported with its third-quarter results on 6 November that Invitium Energy, its joint venture with Blackstone Infrastructure, has agreed all key commercial terms with QTS for about 2 GW of generation for the QTS data center project in Salem Township, Pennsylvania. PPL holds 51% of the venture. The term sheet takes an earlier letter of intent a step further, but it is nonbinding and subject to the usual conditions, and PPL has left the project out of its capital plan and earnings outlook.
Fuel cells and batteries first, gas plants in 2032 and 2033
The supply is to come from two combined-cycle natural gas plants, with fuel cells and battery storage alongside. The mix of the last two is not settled. According to the release, fuel cells and batteries could be in service as early as 2029, while the combined-cycle units are expected in 2032 and 2033.
The initial term is 20 years with several five-year renewals. QTS would pay a fixed monthly amount with annual escalation, which covers the invested capital, the return on it and the fixed operating costs, and variable payments for fuel and other running costs when the plants operate. PPL calls the risk profile "regulated-like". Invitium has also signed a cost reimbursement agreement with QTS that covers specified development costs if certain approvals and conditions are not met.
The release puts no price on the project. MarketBeat's summary of the earnings call gives $5 billion to $7 billion in total, of which PPL's share would be about $2.5 billion to $3.5 billion. Chief executive Vincent Sorgi said on the call that the parties are working towards a full agreement and named no date. Chief financial officer Joe Bergstein does not expect earnings from the project before the units are running. Beyond QTS, Invitium holds reservation agreements for 5 GW of combined-cycle gas turbines; PPL sees $6 billion to $9 billion of possible investment for its share through 2032, not counting fuel cells and batteries.
35.3 GW in the Pennsylvania queue
The same release updates the count of data center requests at PPL Electric, which has now grown for eleven quarters in a row:
- about 35.3 GW in advanced stages, 3.5 GW more than a quarter earlier according to MarketBeat
- 11.4 GW under signed electric service agreements
- 8.5 GW under construction
- 300 MW of contracted load energized at two connected data centers, as stated on the call
In Kentucky the economic development pipeline of LG&E and KU stood at about 14.7 GW through 2032, of which 12.8 GW are data centers; 2.3 GW are under signed reimbursement agreements, 1 GW more than in the second quarter. PPL has raised its capital plan for 2027 to 2030 to $25 billion, about $2 billion above the previous plan, mainly for one more combined-cycle unit in Kentucky. MarketBeat gives 2032 as its planned start of commercial operation. Sorgi said the large-load tariffs in both states make data centers bear the cost of serving them.
Between 300 MW and 8.5 GW
Put the last two figures of that list side by side. In one utility territory, 300 MW are energized and 8.5 GW are being built. Halls fed from the grid still get their standby generation, and the sets for them have to be found in a market where builders book generators two years ahead.
The Salem Township schedule shows the other half of the picture. With combined-cycle plants in 2032 and 2033, whatever the campus does before then will run on the grid connection, on the fuel cells and batteries, or on something temporary. None of the sources says which. A specifier asked to quote for such a site should find out early whether the engines are wanted as emergency plant for a few hours a year or as bridging power for several years, because the emissions equipment, the fuel storage and the noise permit are not the same in the two cases.