Uniper wants to turn its old power station sites into data centre land, and the first deal looks close. The Financial Times reported on Monday, 16 November, that the German state-owned utility is near an agreement to sell or lease one disused site to a data centre developer and is in advanced talks on two more. Investing.com and Data Centre Review summarised the report.
What Uniper is really selling
Chief executive Michael Lewis said Uniper has about 700 MW of secured grid capacity at disused sites. Using IEA estimates, Investing.com writes, that is enough for around seven hyperscale data centres or 70 smaller ones, and Lewis sees much more in the pipeline, possibly at gigawatt scale. His point to the FT was that Europe will not lose the AI race in the laboratory but at the substation.
The company has identified more than ten candidate sites in the UK, Germany, Sweden and the Netherlands, at least five of them in Britain. The best known is Ratcliffe-on-Soar in Nottinghamshire, the coal station that closed in September 2024. In May 2026 Rushcliffe Borough Council approved changes to the site's Local Development Order so that data centres can go up on the southern part before demolition in the north is finished. Council documents from the same month show that Uniper applied to National Grid for a new 720 MW connection there.
No price has been published. UBS analysts put comparable deals at about EUR 1 million per MW, which would value the 700 MW at roughly EUR 700 million, and RWE sold a former British coal plant site to Amazon last year for EUR 203 million. Uniper plans to invest EUR 6 billion in gas plants and data centres by the early 2030s. Germany is preparing to sell a majority stake in the company or list it; Investing.com names Centrica, Equinor and a Brookfield and CPPIB group among those interested. Earlier this month Drax and Brookfield announced a campus at Drax power station, so Uniper is not alone with the idea.
Export connection, import load
Data Centre Review raises the point any electrical engineer would. A power station connection was built to export. A data centre imports, around the clock, so the connection agreement, network reinforcement and parts of the electrical works may have to be redone before the capacity can be used, and what is there may not cover a full campus. The IEA puts EU grid connection waits at two to ten years depending on the country, which is why a connection that needs rework can still be the fastest route.
For the backup plant these sites have a quieter advantage. A former power station sits in an industrial zone, usually with heavy-load access and neighbours who are used to large plant. That does not replace the air permit or the noise assessment for a new generator yard, but the planning discussion starts from a different place than on a greenfield plot next to houses. Ratcliffe's revised development order shows how much of the groundwork is done in the local plan before anyone mentions generators.
Sources: Investing.com (citing the Financial Times), Data Centre Review