Tasmania's House of Assembly voted on Wednesday, 18 November, for a pause on major AI data centre projects until legislation catches up. The next day Premier Jeremy Rockliff said his government would not do it. The Greens motion passed 17 votes to 13 with Labor and six independents, ABC News reports, but it is not binding.
A clean industry or a pause first
Rockliff argued that a moratorium would kill growth, calling data centres a new clean industry that buys Hydro Tasmania's power and helps fund public services, and he warned that stopping projects would bring the state to a standstill. A government spokesperson said plainly that it opposes a moratorium. The government's line is that operators should bring their own renewable energy and that projects will be handled so they do not threaten energy security.
Energy Minister Nick Duigan made the case for Firmus Technologies, which would become the state's largest energy consumer. He said Firmus would pay market rates, pay for its transmission up front and bring hundreds of millions of dollars to Hydro Tasmania, TasNetworks and the state budget. Firmus has one AI data centre under construction at St Leonards near Launceston and two more planned in the north, at Wesley Vale and at Long Reach near Bell Bay. The government is also in confidential talks on six further data centres.
The opposing side brought numbers of its own. Independent MP George Razay said an extra 500 MW of demand would need about 1,500 MW of wind generation, three times the wind capacity installed in Tasmania today. Residents at Wesley Vale have protested over noise, water, electricity use and transparency.
The vote followed a bill tabled on 17 November by Franklin independent Peter George. As the ABC described it, his bill would stop new data centres until questions of location, energy and water are settled, allow them only in designated zones and keep public consultation and appeal rights. George declared shares in Goodman Group, whose development pipeline is largely data centres but which has no Tasmanian proposal. Rockliff pointed instead to the expectations document the government published the week before, which asks for partnerships with new renewable projects, efficient water use and a community benefit fund. Labor leader Josh Willie and the Greens want binding rules before projects go ahead.
Where the generators come in
None of this week's reporting mentions diesel, yet the backup plant is where Tasmania's rules have already been tested. Firmus is appealing a council condition that limits the 276 generators at Long Reach to emergency use, and the state EPA has asked to join that case.
Designated zones, if they come, would settle the question developers find hardest to answer late in a project: how far the generator yard sits from the nearest house. Noise studies and run-hour limits are far easier to agree when that distance is fixed by the zone rather than argued site by site.
Sources: ABC News (19 November), ABC News (17 November)