Fervo Names Eight Geothermal Units for Google's 396 MW in Utah

Fervo Energy has said which machines will serve its contract with Google. In the project update that came with its third-quarter results on 9 November, the geothermal developer assigned eight generating units at Cape Station in Beaver County, Utah, to the 396 MW of grid-connected power it has sold to Google. They are blocks 4 to 11 of the site, and Fervo groups them under the name Cape Google 400. Data Center Frontier, which analysed the update on 11 November, gives mid-2028 for first power from these units and the end of 2028 for the full contracted capacity.

Where Cape Station stands

The first block, rated at 33 MW, went into commercial operation on 30 September. By 9 November block 2 was synchronized with the grid and delivering test power, and block 3 was mechanically complete and in equipment checks. Fervo expects both in commercial operation by 1 January 2027, which would complete a first phase of about 100 MW.

On the eight Google units, Investing.com's summary of the quarterly presentation reports that the drilling campaign is about 18% complete. It also says that a first 50 MW turbine set has passed its factory acceptance test, that recuperators have been delivered and that more than 60% of the air-cooled condenser fans are on site, without stating which blocks this equipment is for. Fervo expects Cape Google 400 to be ready for project-finance debt in mid-2027.

Google pays whether or not the campus is built

The contract is a take-or-pay agreement over 15 years. Data Center Frontier points out that Google pays even if it never builds the data center it has proposed in Beaver County. A framework agreement on top of it gives Google an option on roughly 600 MW more, and that expansion is planned as behind-the-meter delivery straight to the campus under Utah's SB132. The campus still depends on engineering, approvals and a commercial decision by Google.

The figures from the presentation, as Investing.com reports them:

  • Contracted capacity of 1,054 MW and a revenue backlog of about $11.9 billion.
  • Capital expenditure of $256.7 million in the quarter. The forecast for the second half of 2026 was cut to $700-750 million from $850-900 million, which the company puts down to more efficient execution and not to delays.
  • An operating loss of about $43.7 million, and net income of $11.7 million that the report attributes to non-recurring items.
  • A current well design with 15 MW gross per production well, against 3 MW for the first design, and an installed cost target of $5,500 per kW, down from more than $15,000 for the original design.

For people who plan power for data centers, two points are worth keeping. A block of about 400 MW of firm capacity is being built as eight units and not as one machine, so an outage takes out one unit and leaves the rest running. It is the same reasoning that leads others to rows of engines in place of one large block. The other point is the difference between the two halves of the deal. The 396 MW go to the grid, and a campus supplied from the grid keeps its usual standby plant. The 600 MW option would be delivered behind the meter, and there the question changes. Whoever designs that campus will have to say early what covers a lost unit: a grid tie, batteries or standby generating sets. Neither report addresses that yet.

Sources: Data Center Frontier, Investing.com