After an eleven-hour hearing that ran well past midnight, the Stafford County Planning Commission in Virginia voted 4-3 early on 19 November to recommend that all 11 applications behind four data center projects be refused. The projects, Forest Lane, Sims Farm, Sisson North and Sisson South, belong to Peterson Companies and would put about 9 million square feet of data center space on roughly 1,400 acres in the George Washington District, Potomac Local reports. The vote is advisory. The Board of Supervisors decides, and it has not yet set a hearing date.
Four projects, 11 votes
The applications combine rezonings, comprehensive plan compliance reviews and conditional use permits, and each was voted on separately, every time 4-3. FOX 5 DC describes the package as a rezoning from agricultural to heavy industrial use for 37 data center buildings and 14 electrical substations along the Kings Highway corridor. Neither report gives a power figure in megawatts.
The money and water figures used in the hearing:
- County staff put the tax revenue, after the applicant cut 2 million square feet from the plan, at a peak of about $218 million, levelling off at about $193 million at full build-out (Potomac Local).
- The developers told the commission the four projects could bring more than $268 million in revenue by 2036 and nearly 1,200 jobs (FOX 5 DC).
- No potable water would be used for cooling. The buildings would take reclaimed "purple pipe" water from the nearby treatment plant, according to staff.
More than 100 people signed up to speak. Opponents raised the rural character goals of the comprehensive plan, the loss of forest and farmland, water and sewer extensions outside the urban services area, narrow rural roads, the Rappahannock River and the historic ground near Ferry Farm, George Washington's childhood home. Commissioner Kelsey Caudill, whose district includes the sites, moved for denial on the first application. Carlos Bratton, Maureen Siegmund and Marcus Oats voted the other way. They argued that section 3.11 of the comprehensive plan allows data centers outside the urban services area when its criteria are met, and pointed to the mitigation on offer: berms, tree preservation, stormwater controls and stream restoration.
Generator noise taken from the data sheet
One point from the deliberation is worth noting for anyone who prepares these applications. According to Potomac Local, the generator noise figures in the file were based on manufacturer data rather than field tests, and that was raised by the commission.
At rezoning stage this is normal: the generators have usually not been ordered, let alone installed. But a manufacturer's figure describes one machine under defined test conditions. The neighbours will hear a whole yard of them, with exhausts, cooling fans and air openings facing in some direction, sound reflecting off the halls, and monthly test runs. Planning boards now hear about generator noise from other counties, and they ask how the site figure was built up. It helps to show the method openly: which units, what treatment on the air inlet and outlet paths, which test schedule, and a commitment to measure after commissioning. Fort Worth's commission went through the same questions this autumn.
Construction hours would follow the county noise ordinance, 7 a.m. to 10 p.m. on weekdays and 9 a.m. to 10 p.m. at weekends and on holidays. Tighter hours were discussed but not taken forward. Loudoun County has just paused new data center and substation applications for a year, so Stafford's supervisors will not be deciding in a quiet moment.
Sources: Potomac Local, FOX 5 DC