Siemens Energy Sees Gas Turbine Demand Holding Up Through 2035

Is the run on gas turbines a data center bubble? Siemens Energy's management says no, and its own backlog shows why. On the call for its fiscal 2026 results on 11 November, chief executive Christian Bruch said gas turbine orders should continue at roughly the current pace through 2030 and possibly through 2035, Utility Dive reported on 17 November.

65 GW on the books, 42 GW of it new

The company ended its financial year with an order backlog of EUR 164 billion, about $180 billion, and order intake 18.8% above the previous year. The gas turbine backlog stands at 65 GW, and 42 GW of that was ordered during fiscal 2026. Turbine orders slowed somewhat in the fourth quarter; chief financial officer Maria Ferraro put that down to project phasing. US orders rose 70% year on year, with $6.7 billion booked in the fourth quarter alone.

The figure that will surprise some readers is the data center share. Ferraro said customers linked to data centers account for about EUR 15 billion of the backlog, less than 10% of the total, and called the growth story much broader than that. Siemens Energy expects data centers to be about a fifth of the growth in world electricity demand, which it sees rising 60% by 2040. Bruch also said he does not think the backlash against data centers seen in the US midterm elections has dented demand for turbines or other electrical equipment, and that the most advanced economies need to replace about half of their existing grid.

The company plans about EUR 4 billion of new manufacturing capacity by 2030, including a substantial expansion of transformer and switchgear production in North America. A plant under construction in North Carolina is already sold out for its first two years, according to Ferraro. On the service side, revenue from gas turbine service is expected to more than double by 2035, and 20-year service contracts signed this year carry margins five percentage points higher than before.

Read it as a long queue, not a peak

If a turbine maker expects the present order rate to last another five to ten years, nobody should plan a project on the assumption that delivery slots will loosen soon. That has already pushed buyers towards reciprocating gas engines and the second-hand turbine market.

The transformer and switchgear remark is the one we would underline for standby projects. A generator set that arrives on time is of little use if the medium-voltage switchboard or step-up transformer it connects to is a year late, and those come from the same stretched factories that are now expanding.

Sources: Utility Dive, Siemens Energy financial publications