Google has signed a power purchase agreement for 50 MW of geothermal electricity from Quaise Energy, the companies announced on Tuesday, 17 November. The power is to come from Project Obsidian on the southern flank of Newberry Volcano in central Oregon and will serve Google's three data centers in The Dalles, possibly from 2030. OPB reports that it is the first commercial agreement for Quaise, a Texas developer.
Conventional drilling first, millimetre waves later
Quaise's idea is superhot rock: drilling deep enough to reach rock far hotter than conventional geothermal wells use. According to Think GeoEnergy, which works from the Quaise release, phase one of Obsidian is the 50 MW for Google and uses conventional drilling. A second phase targets 250 MW and is expected to be the first commercial use of the company's millimetre-wave drill, which vaporises rock without mechanical contact. Drilling at the site began in July 2026. Utility Dive quotes Quaise as saying its wells are designed for depths of up to 65,000 feet, where rock can exceed 932 °F, and that superhot wells could deliver up to ten times more power per well.
The money is less clear. A Quaise spokesperson told Utility Dive the deal is worth more than $500 million, while OPB says the price was not disclosed. Carlos Araque, chief executive of Quaise, told OPB the site could reach about 1 GW within the next decade. Lucia Tian, who heads advanced energy technologies at Google, described the resource as clean and firm. Quaise raised a $180 million Series B in August.
For Google it is the third geothermal contract in about a year, after 396 MW from Fervo Energy in Utah, which we covered when Fervo named the units, and 150 MW from Ormat for Nevada. Google says its Oregon campuses run on 83% carbon-free energy.
Ten miles of line before anything reaches The Dalles
OPB points to the part that tends to slip: Quaise must build a 10-mile transmission line from the site to the nearest substation at La Pine before the power can enter the grid towards The Dalles. The same report notes that the Bonneville Power Administration, which owns about three quarters of the region's transmission, built a single mile of new line between 2020 and 2025.
Firm geothermal supply on paper does not change what happens inside the fence. The data centers still sit at the end of a long grid path, and a fault anywhere along it is still covered by the UPS and the standby generators on site. What a contract like this changes is the annual energy account, not the size of the backup plant.
Sources: OPB, Think GeoEnergy, Utility Dive