Lead times for large transformers have gone from about six months to more than two years in four years, and a new study says the queue will get longer. Researchers at Johns Hopkins University published a model in Cell Reports Sustainability on 17 November that projects US shortages of transformers, converters and other grid equipment as early as 2027, becoming acute by 2030. Yury Dvorkin and PhD candidate Boyu Yao ran power demand projections against global supply-chain data. The university calls it the first study to quantify the expected shortfall by equipment type and by material.
Three demand cases
The study assumes US electricity use rises 21% by 2030, against historical growth of one or two percent a year. Data centers, electric vehicles and electrification drive the increase, and data centers alone could account for up to two-thirds of the equipment shortfall. The results by scenario, as given in the Johns Hopkins release and by Fortune:
- Baseline growth: probably enough transformers by 2030, but other grid-supporting equipment about 16% short.
- High demand: over the next four years, transformers almost 15% short and other critical equipment 30% short.
- High demand with trade disruption: if materials from unstable trading partners fall by up to 70%, the gaps grow to about 25% for transformers and 36% for the rest.
Dvorkin is less relaxed than the baseline line suggests. In the release he expects transformer shortages by 2030 even without the most aggressive demand growth. The materials in question are copper, steel, nickel, aluminium and manganese. Copper runs short first, from next year; steel and nickel will be close to impossible to source by 2030, the researchers say. Fortune adds that only one US mill makes the grain-oriented electrical steel used in large power transformers.
The remedies proposed are modest. Low-cost sensors that track transformer load and temperature would let existing units run on measured instead of conservative fixed ratings, and the team expects that to ease the shortage slightly. Beyond that: recycling of materials from retired units, and more standard designs so that one transformer can replace another. On who gets the scarce units, Dvorkin is blunt: utilities will compete with the data center industry, and the transformers will go first to whoever pays the highest premium.
The transformer behind the generator
For a standby plant this is not only the utility's problem. Medium-voltage generator schemes have their own step-up transformers between the alternators and the switchgear, built in the same factories from the same electrical steel. A genset delivered on time does not help if its transformer turns up a year later and the plant cannot be load tested. Put the transformers on the long-lead list at the same moment as the engines, get the delivery date confirmed in writing, and avoid one-off ratings where a standard unit would do. The last point is the same one the researchers make for the grid.
Fortune sets the study against JPMorganChase's estimate that the US grid needs about $1 trillion of investment through 2035, and against the $1.9 billion the Department of Energy committed to 31 projects in September. Interconnection waits are already counted in years. If the model is right, hardware may set the pace even where the queue does not.
Sources: Johns Hopkins University (EurekAlert), Fortune