Ex-FERC Chair: Data Center Diesel Backup Is Turning Into Routine Use

Thirteen times this year, seven of them in PJM, US authorities have invoked emergency powers that allow grid operators to call on the backup generators of data centers and other large loads. The count comes from an opinion article that Utility Dive published on 10 November. Its authors are Jon Wellinghoff, a former chairman of the Federal Energy Regulatory Commission, and Antonio Baclig and Ben Kaun, chief executive and chief commercial officer of Inlyte Energy. Their argument is that diesel sets built to stand idle are drifting from backup into regular service.

One thing has to be said before the figures. Inlyte develops iron-sodium batteries for long-duration storage, and Wellinghoff sits on its advisory board. The article ends by recommending the kind of product the company sells.

What the authors count

The record they put together is worth reading whatever one thinks of the remedy. In January the Department of Energy authorized grid operators to draw on as much as 35 GW of idle backup generation at large facilities. On 2 July, under a heat dome over the Mid-Atlantic, PJM recorded its highest unrestricted demand so far, 168 GW. Utility executives in Northern Virginia said they came within minutes of having to call on the generator fleets of the data centers there. And from 13 to 16 October, in a warm spell during the autumn maintenance season, the DOE issued another order at PJM's request - the one we reported on at the time.

The authors also recall what such running sounds like to the neighbours. Residents of Loudoun County compared generators that ran for more than 24 hours in an earlier emergency to airplanes landing.

The Virginia study behind the 45% figure

For emissions the article leans on a white paper from Virginia Commonwealth University. According to the authors it found that the diesel generators of Northern Virginia's data centers, run up to their permitted limits, would raise the region's emissions of nitrogen oxides by 45%. The article says "nitrous oxides"; NOx is evidently what is meant.

The paper's own summary is more careful in its wording. Damian Pitt and his co-authors at the university's Institute for Sustainable Energy and Environment write that the emissions of a single data center are small, but that the more than 100 facilities in the region add up. If all of them emitted at the maximum their air permits from the Virginia Department of Environmental Quality allow, the total would far exceed that of any other facility in the region. Exposure follows income and education, they found, and not race.

Their answer: longer batteries

Virginia has ordered its environmental regulators to review the cumulative effect of data center backup generation and to look at alternatives, among them batteries on and off site, load flexibility and fuel cells. The authors go further. Lithium-ion systems installed today last two or four hours, they write, which is not enough for backup, and they call for storage that can cover 24, 48 or even 72 hours. They name no project and no cost.

Leave the batteries aside and the count still matters to anyone specifying standby plant in PJM territory. A set that is called by the grid operator several times a year no longer has the duty of a set that runs for its monthly test. That changes what the permit should cover. From 4 November Virginia already asks for Tier 4 equivalent emissions from new data center generators, and exhaust aftertreatment that is used on every start wants its reagent supply and its warm-up behaviour looked at more closely. Noise is then judged over a night of running instead of a test hour at noon, and the fuel contract has to assume that the tanks are refilled in the same week in which every neighbour is ordering too.

Sources: Utility Dive, Virginia Commonwealth University

Other News