Used Gas Turbines Sell Fast as Data Centers Face Six-Year Waits

A broker sold two used 14.5 MW gas turbines from Solar Turbines, the Caterpillar subsidiary, for $12.5 million. Bought new, the pair would have cost about $35 million and taken five years to arrive. The sale is one of the examples in a Reuters report of 9 November, relayed by Decrypt and Startup Fortune, on how utilities, developers and data center builders are combing the secondary market for gas turbines, bringing mothballed machines back into service and buying power packages built around aircraft engine technology.

Six years for a new machine

The reason is the order book. Reuters cites the consultancy Wood Mackenzie: a new gas turbine for the US now takes about six years on average, and delivery talks are about 2030 and 2031. Worldwide, orders stand above 100 GW while the manufacturers can build 60 to 70 GW a year. Siemens Energy, GE Vernova and Mitsubishi Heavy Industries all say that orders are running ahead of what they can produce.

Prices have followed. Brokers and analysts quoted by Reuters put a used turbine in good condition at $1.5 million to $1.7 million per MW and a refurbished one at around $1.3 million, against $2 million to $2.5 million per MW for a new unit. Ana Amicarella, chief executive of EthosEnergy, called the secondary market very hot and said asking prices keep rising. Darayus Pardivala of Sulzer's US aftermarket business said his team gets a request for used turbines for data centers every few weeks.

Aeroderivatives and engines take a share

Crusoe ordered 13 aeroderivative units from ProEnergy in April, about 650 MW in total. Startup Fortune, citing Tom's Hardware, adds that ProEnergy has delivered more than 1 GW of its PE6000 packages to two data center customers. Reciprocating engines are part of the picture as well: Wärtsilä told Reuters it has booked about 3 GW of US data center orders since spring 2025 for generating sets driven by gas engines.

How much of all this is running is another matter. An analysis by Cleanview from mid-2026, cited by Decrypt, counted about 90 GW of proposed on-site generation at US data centers and about 2 GW in operation. Decrypt also notes the EPA's position that stationary turbines and engines used by data centers fall under federal air pollution standards.

A used turbine arrives as a machine, not as a plant. Its inlet filter house, enclosure, exhaust stack and silencers were designed for another site, with another climate, another noise limit and another permit. The limits that count are those of the place where it will run next, and the papers that prove what the old package can do are often thinner than the buyer would like. Before the price per MW is compared with a new unit, it is worth listing what has to be rebuilt around the machine: inlet and outlet silencers, exhaust treatment, controls and the acceptance tests on site. That list is also where the time gained on the turbine can be lost again.

Sources: Decrypt (via Yahoo Finance), Startup Fortune