CDC Data Centres now wants approval for its whole Kemps Creek campus in western Sydney at once. The revised scheme for 845-901 Mamre Road covers six data centre buildings, KC1 to KC6, with 1,008 MW of IT capacity and a combined peak power requirement of about 1.4 GW, Real Estate Source reported on 15 November. Penrith City Council asked for the six buildings to be brought forward under a single application.
From one building to six
The project began as a single building on an 88.33-hectare holding. With an added allotment of 29.14 hectares at 845-857 Mamre Road the site now measures 117.47 hectares. The six buildings, two storeys each and up to 25.5 m high instead of the four levels and 35.2 m first drawn, would hold 29 data halls. An administration building, security infrastructure and an on-site substation complete the plan.
The indicative split, as reported:
- KC1, KC2 and KC3: 168 MW of IT capacity each, built first together with the substation and the administration building.
- KC4: 144 MW; KC5: 120 MW; KC6: 240 MW, to follow.
One substation and one Transgrid connection would serve the whole campus and are designed around its final capacity. A collector road that would have cut through the site moves to the western boundary. The NSW Planning Portal lists the project as State Significant Development SSD-133677993 at the stage of preparing the environmental impact statement, which is to cover the larger campus, the cumulative impacts and the electricity connection. The original application of July 2026 named a $1.8 billion development with 280 ongoing jobs; revised figures have not been set, the report says.
One approval for the whole site, standby included
Neither the article nor the portal entry says anything about backup power yet. That will come with the EIS, and at this scale it is a big chapter. For comparison, a different data centre approved at Kemps Creek in July 2023 under SSD-10101987, two data storage buildings, lists 61 generators and 30 diesel storage tanks in its description on the same portal.
Putting six buildings into one consent has a practical side for the backup plant. Generator numbers, fuel storage, noise at the boundary and the cumulative air assessment would then be judged once for the full build-out rather than building by building, and the later phases inherit whatever the first approval allows. For whoever specifies KC4 to KC6 in a few years, the conditions will already be written. Australia's other big projects are running into their power questions in public, from South Australia's gas debate to the off-grid Project Ares.
Sources: Real Estate Source, NSW Planning Portal (SSD-133677993), NSW Planning Portal (SSD-10101987)