Oakland Extends Its Data Center Moratorium to October 2027

Oakland will not approve a new data center for most of next year. On Tuesday evening, 10 November, the City Council voted 8-0 to extend its moratorium by 10 months and 15 days, to 5 October 2027, East Bay Insiders reports. The original 45-day pause was approved on 6 October and would have run out on 20 November; from that day the city would have had to process applications again under its existing zoning.

A planning code with no word for data centers

That zoning is the difficulty. Oakland's planning code does not define data centers as a land use at all, and according to SFist, which cites The Oaklandside, it is said to hold no specific rules on their energy and water use, their noise or their backup generators. The extension keeps land-use approvals suspended while planners work out where such buildings may go, how large they may be and what they may do to their surroundings.

Planning and Building Director Bill Gilchrist told the council that his department has made substantial progress but needs more time, more studies and more outside expertise. His staff are reading the regulations other Californian cities have adopted and are consulting PG&E, the East Bay Municipal Utility District and Ava Community Energy on electricity and water capacity. Community meetings are to follow in the coming months, NBC Bay Area reports.

The measure comes from Councilmember Carroll Fife, whose West Oakland district is seeing interest from large technology companies. She said the pause is there to protect residents and is not a rejection of technology or economic development. One project is already affected: plans by Behring Companies for a data center inside a downtown office building are on hold, SFist writes. A survey of 424 West Oakland residents by the group Care 4 Community Action found 73% in favour of a complete ban on new AI data centers. Zoe Jonick of 350 Bay Area called the extension a first step and told NBC that advocates would like it to last for good.

San Francisco: 800 MW of peak on 1,000 MW of lines

Across the bay the Board of Supervisors is expected to take up a 10.5-month extension of San Francisco's own 45-day pause next week. SFist, drawing on the San Francisco Chronicle, summarizes a Planning Department report written for that debate:

  • The city's transmission capacity is about 1,000 MW, and peak demand reached roughly 800 MW last year.
  • A 50 MW data center could use as much electricity as 25,000 homes.
  • Electrification of buildings and other development could add up to 20 MW of demand a year.
  • A major new transmission line could take up to ten years.

San Francisco has three stand-alone data centers today, and developers have looked at the closed San Francisco Centre mall, SoMa and the Dogpatch. The report suggests power limits, additional utility assessments for larger projects and restrictions on stand-alone facilities in residential and commercial areas, and it takes no position on the moratorium itself. SFist adds, again from the Chronicle, that backup generators could bring more air and noise pollution to neighbourhoods that already carry more than their share.

The two cities are not alone. East Bay Insiders lists Richmond, which extended its moratorium by 22 months and 15 days, Oakley and Hayward, and says San Jose and Santa Clara are reviewing their rules.

What kind of rule comes out of such a pause can be seen in Minneapolis, where the draft ordinance demands a sound attenuation plan for indoor and outdoor equipment. A Bay Area project has one more authority to satisfy: the regional air district, whose permit for the standby engines is separate from anything the planning code will say. In a converted office building in the middle of a city, the route of the exhaust line, the place for the fuel and the hours allowed for test runs are worth settling before the lease is signed. A year of moratorium is enough time to do that work on paper.

Sources: East Bay Insiders, NBC Bay Area, SFist