Data centers that take 50 MW or more from Duke Energy in North Carolina will be billed under a rate schedule of their own. The North Carolina Utilities Commission approved two-year rate plans for Duke Energy Carolinas and Duke Energy Progress on Monday, 16 November, and used the orders to set separate terms for large data centers for the first time. The new rates start on 1 January 2027 and apply to existing data centers as well as new ones, WFAE and WRAL report.
What the schedule asks of a data center
According to WRAL, the order requires:
- demand charges on at least 75% of the contracted demand, even if the site draws less;
- minimum contracts of 10 years, or 15 years for 100 MW and above;
- up-front payment for infrastructure built only for that facility, and security for the transmission upgrades it needs;
- exit charges for early termination, and recovery of generation costs;
- temporary demand reductions under certain grid conditions.
WFAE adds that Duke must track the cost of serving data centers as if they were a customer class of their own. The commission pointed to the scale and speed of the new load and to the fact that data centers draw power about 90% of the time, which other industrial customers do not. In the order's logic the risk sits either with existing ratepayers, who did not create it, or with the data centers that do. A Stranded Generation Charge assigns the cost of new power plants to the data centers.
Behind this are large numbers. Between March 2024 and April 2026 Duke signed contracts for 6.7 GW with new large customers in North and South Carolina, 92% of it for data centers. Duke expects large data centers to make up 9.2% of Duke Energy Carolinas' peak demand by 2035. On the same day the commission approved Duke's long-term plan, which keeps some coal plants running longer and adds almost 3,850 MW of new gas generation next to solar and batteries.
Duke said in an SEC filing that it is still evaluating the data center provisions. Will Scott of the Environmental Defense Fund called the financial requirements a big step forward and wants data centers to pay for their own clean energy and batteries. Two weeks earlier Florida's regulators had gone the other way and rejected Duke Energy Florida's large-load tariff.
The demand reduction clause and the generator yard
Most of the order is work for lawyers and finance teams. Two points reach the people who plan site power. A 15-year contract with a floor under the demand charge makes a developer think harder about phasing: how many MW to contract on day one, and how the rest of the campus is covered until grid capacity is there. That is where bridging generation and rental power come in, each with its own permit and fuel logistics.
The other point is the clause on temporary demand reductions. Wherever a utility can ask a large customer to cut load, someone soon asks whether the standby gensets could carry the site for those hours. Whether the air permit allows it is a separate question, and in our view it should be answered before the first one. The debate over backup diesel turning into routine use started exactly there.