The power contracts for Google's planned data centers in Oklahoma are now in court. Three Republican state representatives, Tom Gann, Rick West and Kevin West, have asked the Oklahoma Supreme Court to review the Oklahoma Corporation Commission's approval of OG&E's agreements with Alliance Site & Grid, a wholly owned Google subsidiary, The Oklahoman reported on 15 November. The agreements cover the supply of large amounts of power to three planned Google-affiliated data centers.
The complaint is about process
The lawmakers argue that OG&E's customers had no real chance to intervene before the commission approved the deal. According to the report, the procedural schedule came out on 11 June, ten days after the deadline for third-party intervention, and customers were only told directly about a pending hearing in August. The commission says the 1 June deadline had been set in a separate order nine days earlier. The petition also says hundreds of pages of Gann's public comments never entered the record, and it asks the court to find that one commissioner voted unlawfully. It is Gann's 17th petition against commission decisions since 2024.
Gann also objects that the commission's order classes the agreements as highly sensitive confidential information, so the costs and risks for other customers cannot be seen. He points to HB 2992, which requires separate tariffs for data centers.
What Google pays, according to OG&E and the commission
- All of the cost of transmission and distribution built only to serve Google, and all contracted costs whatever its actual consumption, with a minimum charge.
- Its share of the generation needed, including construction work in progress if that is approved for recovery.
- OG&E has to compare the cost of serving Google with a case without it and report certain revenues; the commission keeps the right to look at cost allocation again in later rate cases.
OG&E's application of 1 May also asked to buy power from two Oklahoma solar farms, assigned to the Google sites. The utility has said the agreement became the model for a special rate structure for future large-load customers. The commission declined to comment on the legal arguments while the case is pending.
Regulators in Florida rejected a large-load tariff outright and Oregon created a separate rate class. Oklahoma's case is narrower, it is about who was allowed to speak before the deal was signed. For developers the lesson is practical: a supply contract approved in a confidential proceeding can still be reopened, and the grid date it promised moves with it. Backup plant sized and permitted around that date has to wait as well, or run longer than anyone planned.