Oregon Gives Pacific Power's Large Data Centers Their Own Rate Class

From 1 January 2027, a data center of 20 MW or more in Pacific Power's Oregon service area will be billed in a customer class of its own. The Oregon Public Utility Commission approved the tariff on Friday, 13 November, KTVZ reports. The class takes in facilities that use, or are able to use, 20 MW or more for computing infrastructure, data processing, web hosting and related services, and the cost of serving them is assigned to those facilities directly.

Long contracts and the full bill

As the Bend station describes the tariff, these customers sign long-term service agreements and pay for all the electrical infrastructure and power services their operation needs. The stated aim is more financial certainty for the utility's existing customers. The decision implements the POWER Act, a state law passed in 2025 in response to concern about what new data centers do to electricity bills.

The approved text goes back to an agreement reached this autumn between Pacific Power, the commission staff, the Oregon Citizens' Utility Board and the Green Energy Institute. Rick Link, Pacific Power's senior vice president of planning and regulation, said growth in Oregon has to happen in a way that keeps power affordable for today's customers, and that new large users will now carry their own costs. The report gives no rates, no vote count and no figure for the data center load the utility expects.

PGE's Schedule 96 came first

Portland General Electric went through the same process earlier. On 7 May the commission approved its framework for loads above 20 MW, Schedule 96, and Utility Dive listed the main terms:

  • customers pay all distribution upgrades built to serve their projects;
  • generation and transmission demand charges are set at no less than 90% of contracted capacity, even when less is used;
  • contract terms grow with project size, from 10 years up to 30 years for loads of 220 MW or more, and leaving early carries penalties;
  • projects above 100 MW pay a surcharge of 1 cent per kWh, which funds programs for residential and low-income customers.

At the time, Utility Dive noted that the Pacific Power case was still open and had been challenged by consumer advocates. Whether the new Pacific Power tariff uses the same minimum-demand and contract-term rules is not stated in the KTVZ report.

Tariffs of this kind change the design of a site long before anyone orders a generator. Where the utility bills most of the contracted capacity whether it is used or not, an owner will contract carefully and then look at what can be done on site: shaving peaks, running on-site generation for some hours, carrying part of the load during grid events. Each of those puts the standby plant to work in a way an emergency-only air permit may not allow, so the power contract and the permit should be read side by side, by the same people. Florida's regulators turned down Duke's large-load tariff; Oregon now has one in place for both PGE and Pacific Power.

Sources: KTVZ, Utility Dive