Power Solutions International has tied down its supply of 22-liter gas engines for the next two years. On 9 November the company, based in Wood Dale, Illinois, amended its supply agreement with HD Construction Equipment (HCE), an affiliate of HD Hyundai, to cover GV22TI natural gas engine long blocks for 2027 and 2028. PSI's 8-K filing puts the agreed volumes at about $121.9 million, at a unit price that stays fixed until the end of 2028.
Price, advance payments and a 90% floor
The filing is more open about the commercial terms than such announcements usually are:
- Price: the unit price holds for every GV22TI long block ordered and shipped on or before 31 December 2028 and can only be changed if both sides agree in writing. The price itself is not disclosed.
- Deliveries: a monthly schedule is attached to the amendment.
- Advance payments: PSI pays HCE 10% of each year's contract value up front, by 30 November 2026 for the 2027 volume and by 30 June 2027 for the 2028 volume. HCE gives the money back as a 10% reduction on that year's invoices.
- Shortfall: if PSI buys less than 90% of the scheduled volume over the 24 months, the two companies have to agree on a recovery mechanism, which may include a price increase in 2029.
In its press release PSI lists the other side of the bargain among its risks: it depends on HCE delivering on time, and it has to make the advance payments before its own customers have paid.
What PSI gets for the money
A long block is not a finished engine. The Elec, a Korean trade outlet, describes it as a partly assembled engine with cylinder block, pistons and crankshaft but without the fuel and ignition systems. PSI completes the engines and builds them into stationary power generation systems for data centers and other critical infrastructure, and it presents the amendment as a step in its Power Boost 2030 strategy. The underlying agreement dates from 11 December 2007 and was signed with Doosan Infracore, later HD Hyundai Infracore; it was assigned to HCE with effect from 1 January 2026.
Seen from Korea
HCE disclosed the deal a day later, on 10 November, and the Korean reports treat it as a new order. The Elec puts it at 165.5 billion won, BigGo Finance at about 160 billion won or $118.9 million; PSI's filing is the only one of the sources that gives a dollar figure taken from the contract. Both outlets count it as HCE's second North American engine order within a month, after a contract of about 390 billion won with ERock in October. BigGo adds that HCE's new engine plant in Gunsan, completed in October, is laid out for 1,250 engines a year in the 1 to 3 MWe class, and that the company is aiming for 2.5 trillion won of engine revenue by 2030. We reported on the first start of its 77-liter DX77 last month.
The Elec explains the demand with the shortage of large gas turbines, which is pushing gas engines forward as an alternative for AI data centers in the United States.
For anyone buying gas gensets for 2027 or 2028, the terms say more than the headline. A packager that pays 10% up front and commits to 90% of a two-year schedule is telling you where its bottleneck is. The useful question in an enquiry is therefore whether the engine slots behind a quoted lead time are actually contracted. And the long block is only the start: the gas train, the exhaust system and the enclosure each have their own lead time, and none of them is covered by an engine supply agreement.
Sources: Power Solutions International (Form 8-K, SEC), Power Solutions International (press release), The Elec, BigGo Finance