Google is offering to pay for thicker capacity on wires that Ohio's utility was going to replace anyway. On 19 November Google and Ohio Power Company, the American Electric Power subsidiary based in Gahanna, filed a joint proposal with the Public Utilities Commission of Ohio. Under it Google would fund the full incremental cost, put at $10.8 million, of fitting advanced conductors instead of standard ones on 15.5 miles of ageing transmission line in Columbus.
Paying the difference on a project already in the plan
The lines in question are about 50 years old and were already due for an upgrade. The two companies call the arrangement a transmission participation agreement: the large customer does not build its own line and does not wait for a rate case, it pays the extra over the utility's planned project for a conductor that carries more power on the same route. CTC Global, whose ACCC conductor is to be used, says AEP has completed more than 30 projects with that conductor since 2005, covering over 3,700 km.
What the filing claims for the money:
- 24 MW that Google has already contracted for would be delivered about two years early;
- once the planned 765 kV buildout in Central Ohio is finished, the upgraded corridor is expected to free more than 700 MW of additional capacity;
- lower energy losses on the lines, and a slight reduction in the transmission costs paid by other customers.
Google adds $1 million for lineman training, an installation curriculum for advanced conductors and manufacturing apprenticeships in Ohio. The project still needs the PUCO and the Ohio Power Siting Board; if both approve, it is expected in service by late 2028. Amanda Peterson Corio, Google's global head of energy and power, presented it as a way for data centers to add transmission capacity years faster. Marc Reitter, president of Ohio Power, spoke of freeing future corridor capacity for the region.
T&D World sets the deal against the other route utilities are taking with data centers, the large-load tariff with long minimum terms and exit charges. It cites a Southwestern Public Service proposal in Texas that would tie large customers to commitments of at least 15 years. The Ohio model asks for a one-off capital payment instead of a long take-or-pay contract.
Two years earlier changes the site schedule
For a 24 MW building, getting grid power two years ahead of the original date is not a small shift. Everything behind the utility connection has to move with it: the standby generators, their air permit, the fuel deliveries for first fill and the integrated tests. Where the backup plant was planned around a late grid date, or around temporary power until the line arrives, an early connection turns the gensets back into plain emergency plant. They still have to be commissioned, load tested and signed off before the first IT load goes in, only sooner.
The figure to read carefully is the 700 MW. It depends on the 765 kV buildout being finished first, so it is corridor capacity for later, not capacity anyone can count on in 2028. Anyone planning a campus along that corridor should ask Ohio Power which part of the gain is available on which date.
Sources: Google, T&D World, CTC Global