One week after Oakland, San Francisco has done the same. On 17 November the Board of Supervisors voted unanimously to extend the city's moratorium on new data centers by at least 10 months and 15 days, Mission Local and SFist report; the San Francisco Standard says the pause now runs until next September. Supervisor Connie Chan was absent. The extension takes effect ten days after the vote unless Mayor Daniel Lurie returns it sooner. He could veto it, and the board could override him with a four-fifths majority.
Shamann Walton, the District 10 supervisor who introduced the original 45-day moratorium in October, sponsored the extension. City staff say no building or planning applications for new data centers are pending. Walton's reply was that an empty queue is no reason to let the pause lapse, and that the city should also look at a permanent ban.
A report that could not count the buildings
The vote rested on a Planning Department report that describes itself as an initial assessment. Its main points, as reported by the three outlets:
- peak transmission capacity into the city is close to its limit, and new data centers would compete for power with housing, hospitals and businesses;
- the city has no complete inventory of data centers; staff identified three stand-alone facilities, two of them on Paul Avenue in Bayview, an area with a long history of poor air quality;
- the report could not say how much water data centers use;
- it recommends banning stand-alone data center permits in some areas, such as residential and commercial districts, updating the city's definition of a data center, which dates from 2001, and requiring projects to assess their impact on the surrounding community.
Mission Local and SFist note that NOVVA had planned to expand its facility at 400 Paul Avenue from 9 to 36 MW by 2028; those plans are on hold. Sites mentioned in the debate include a plot in Dogpatch and the closed SF Centre mall downtown. Rudy Gonzalez of the Building and Construction Trades Council wrote against a permanent ban and asked for a path to approval with enforceable environmental and labour standards instead.
Five notices for one generator yard
The detail with the most practical weight is in the Standard's report. One of the Bayview facilities has five active notices of violation from the Bay Area Air District this year for its diesel generators. They cite non-compliance with permit conditions, expired permits and the 35-hour run-time limits. The Planning Department report itself lists air pollution and noise from backup power equipment among its concerns.
None of those notices is about engine technology. They are about paperwork and hours: permits that lapsed, conditions not kept, running time not tracked against the limit. These are the cheapest problems an operator can avoid, and in San Francisco they have become part of the political case against the whole building type. The minimum is a run-hour log the air district can read at any time, permit renewals entered in the maintenance calendar, and test runs planned against the annual limit instead of added up in December.
With Oakland's pause running to October 2027, both sides of the bay are now closed to new projects while their rules are written.