Kraft Group Backs a 900 MW, $16 Billion Data Center Plan in Sutton

Sutton, a town of fewer than 10,000 people south of Worcester, Massachusetts, has been handed a proposal larger than anything the state has seen: a data center campus of ten buildings and about 900 MW, which its developers value at $16 billion. It is backed by the Kraft Group and a packaging company that CBS Boston names as United Global Packaging Group, both affiliated with New England Patriots owner Robert Kraft. On Tuesday, 10 November, the Select Board heard the town manager's presentation in a hall with standing room only. Residents shouted "Kill it now", Banker & Tradesman reports, and according to CBS one man was led out by police.

Ten buildings, the first 180 MW in 2029

No application has been filed. What exists is a memo from Town Manager Austin Cyganiewicz to the Select Board, which calls the proposal tentative. The two reports take these points from it:

  • The campus would stand off Boston Road and Providence Road and reach about 2.5 million square feet.
  • The first phase is two buildings with 500,000 square feet and 180 MW, supplied from the regional grid, possibly complete in 2029.
  • CBS has two more buildings opening each year through 2033; Banker & Tradesman puts the full 900 MW at 2035.
  • At full build-out the town would collect $27.8 million a year in property tax. Its tax levy for 2027 is $32 million.

The memo expects the money to show up mainly as lower bills, about $2,300 less for an average single-family home in fiscal 2031 and about $5,800 less in fiscal 2035. For scale, Banker & Tradesman notes that the largest data center in Massachusetts today, the Markley Group's building at 1 Summer Street in Boston, has 30 MW, and that the whole state has 168 MW in 58 facilities, a count it takes from Baxtel Advisory.

Power and water are still blank

The developers have told the town that they are talking to ISO New England about the power and looking at treated wastewater for cooling. Details on power, water, equipment and the effects on the site are still to come, CBS writes. Under the guidelines of Governor Maura Healey's administration the developers are responsible for energy supply, connections and grid upgrades. An executive order from September also requires a community benefits agreement with the host town, and in June the state halted the sales and use tax break for data centers that it had introduced in 2024.

The town manager's schedule runs three things side by side: talks on that agreement, a technical review paid for by the developers, and the drafting of a zoning bylaw for data centers, which Sutton does not have. The bylaw would set limits for noise, vibration, light and heat and rules for screening. A town meeting vote could follow in May. Select Board member Christine Watkins said the parallel timetable feels like a done deal. Her colleague Jesse Limanek, who lives six houses from the parcel, wants to visit operating data centers and talk to their neighbours first, and asked for enforceable tools to hold the developers to account. State Representative Joseph McKenna said he would not refuse the project simply because it is new, but that the concerns about water, noise and energy have to be answered. The town and the Kraft Group declined to comment to WBZ-TV.

Neither report says a word about backup power, and that is the gap we would look at first. On a campus of this size the standby generators are usually the equipment that needs an air permit, and on test days they are among the loudest things on the site. Sutton is about to write its noise limits into a bylaw before anyone has seen an equipment list. Whoever drafts it should ask the developers now how many sets are planned, where they will stand and how often they will be tested, because the figures in the bylaw are the ones the generator enclosures and the inlet and outlet silencers will later be measured against at the property line.

Sources: CBS Boston, Banker & Tradesman

Other News