This comparison comes from an insurance broker, not a utility, which says something about who is now pricing the risk. Howden, working from US Energy Information Administration and S&P Global data, finds that power supplied to US data centers has grown by an average of 19% a year since 2000, while US grid capacity has grown by 2% a year. The Register reported the analysis on 11 November; Fortune came back to it on 22 November with comments from Marsh.
From 0.1% to 5% of US grid capacity
On Howden's figures data centers accounted for about 0.1% of US grid capacity in 2000 and about 5% in 2025. To hold that share through 2030 at current growth rates they would have to source up to 58% of their power off the grid, roughly 110 GW of behind-the-meter capacity. Howden does not expect that. It expects a mix: more reliance on the grid, slower development at sites short of power, and alternative supply. The Register points out that the Howden chart uses different scales for the two lines, 1,400 GW for the grid and 80 GW for data centers, so the curves look closer together than they are.
For the largest and most power-constrained projects, Howden puts the cost of a two- to six-year grid delay at $800 million to $2.4 billion in revenue not earned. Stuart Adam, its head of natural resources, says developers increasingly look beyond the conventional grid connection, and that on-site generation brings new operational and financial exposures, because the operator takes on responsibility for its own power plant.
Kathryn Burke, who leads US specialty energy and power growth at Marsh, told Fortune she expects around 50% to 60% of data center projects to slip beyond the one-to-two-year timelines their developers are counting on. Fortune also cites BloombergNEF: about 2 GW of on-site gas generation was running at data centers worldwide in March, and BNEF has since tracked 181 GW of gas-fired generation announced alongside data centers, more than 90% of it in the US.
What an underwriter will ask about the generators
The insurance view is the useful part here. A backup generator that runs a few hours a year for tests is one risk. An on-site plant that carries the load for months or years while a grid connection is pending is a different one, and brokers are now saying so in public. Expect underwriters to ask what an O&M contractor would ask: running hours per year, maintenance intervals, spares held on site, how much fuel is stored and how it is resupplied, who is responsible when a unit trips. For gas-fired bridging power add the gas supply contract. For diesel that sits in tanks for long periods, add fuel quality.
Earlier this month a former FERC chair argued that diesel backup is drifting into routine use at data centers. Howden's numbers make it hard to see that drift reversing soon.
Sources: The Register, Fortune