Madison, Wisconsin, wants no hyperscale data centers at all. On 20 November the city announced that an ordinance restricting new data centers, with an outright ban on hyperscale campuses, will be introduced to the Common Council on 24 November. Mayor Satya Rhodes-Conway is behind it. The city's one-year data center moratorium runs out on 24 January 2027, and according to the city the present zoning code would give it no way to control the size or location of a modern facility once that happens. The moratorium cannot legally be extended indefinitely.
Size caps and distances instead of a moratorium
The draft came out of months of staff research and community feedback during the moratorium. The city lists these restrictions:
- no hyperscale data centers and no data center campuses; campuses are ruled out by a 1,000-foot separation between lots that carry data centers above 10,000 sq ft and by a cap on total data center floor area per lot;
- a hard limit of 75,000 sq ft for any new data center, and no data centers of any size in residential zones;
- from 50,000 to 75,000 sq ft only in industrial-type zones, at least 500 ft from residential, mixed-use or commercial districts and 300 ft from other non-industrial districts; from 10,000 to 50,000 sq ft only in employment and campus institutional districts; smaller ones only in certain business and commercial areas;
- no data centers on the ground floor of buildings in most of the city.
The mayor said residents are right to worry about a powerful industry dropping a data center into the city without accountability, and that the proposal still leaves room for legitimate computing uses. She also asked state lawmakers to pass data center rules, since Wisconsin law limits what a municipality can do on its own. The city says there is no active proposal for a new data center in Madison and no application on file.
The timetable: no debate at the introduction on 24 November, then the Plan Commission on 30 November, the Business and Economic Resources Committee on 16 December, the Sustainable Madison Committee on 21 December, a second Plan Commission review on 11 January and the Common Council vote, with public comment, on 12 January 2027.
Walls round the generators, a noise plan before the first pour
Two points in the draft concern the plant yard directly. Any new data center above 10,000 sq ft must hand in a Noise Mitigation Plan showing that it will meet the city's noise ordinance, and it must do so before construction starts. External mechanical equipment and backup generators at those sites must be surrounded by solid walls to limit sound. A separate ordinance is to raise the fines for breaking the noise code.
A 10,000 sq ft threshold is low. It catches enterprise and edge buildings with a handful of standby sets, not only large halls, so the acoustic work moves to the permit stage for small projects too. In practice the genset model, the enclosure and the silencing of the air path have to be settled before there is a construction drawing, and a solid wall around the yard still has to let the cooling air in and out. Minneapolis took a different route with its existing-buildings rule, which shows how far apart two Midwestern cities can land on the same building type.
Sources: City of Madison