Five Grid Operators Offer Data Centers Non-Firm Service at FERC

A data center that agrees to be switched off when power gets expensive can be connected sooner. That is the common thread in the answers five US grid operators sent to the Federal Energy Regulatory Commission this month. ISO New England filed on 13 November; CAISO, MISO, NYISO and PJM followed on 16 November, all responding to the show-cause orders FERC issued on 18 June on how large loads should be connected. SPP's response was due on 20 November. POWER magazine notes that the operators appear ready to accept 50 MW as the threshold for a large load.

Where each operator sets the trigger

The interesting differences are in the non-firm service, the part of the load that can be interrupted while the grid catches up. According to POWER and the American Public Power Association:

  • MISO proposes a Grid Responsive Integration Transmission Service. A 500 MW facility could, for example, take 200 MW firm and up to 300 MW non-firm. The non-firm share is cut when the local price exceeds $100/MWh, and in any case when a capacity advisory is declared. MISO says the threshold still allows service in more than 95% of hours.
  • ISO New England offers firm, interim and non-firm contract demand, with re-dispatch of interim and non-firm customers at $250/MWh. On 2021-2025 prices that level was reached in about 1% of hours. Customers who want firm service bring their own new capacity. The assessment process is to start on 1 June 2027.
  • NYISO sizes firm withdrawal from a project-specific resource adequacy study over ten years. Loads that degrade adequacy by 25 MW or less get all the firm service they asked for; above that, part becomes non-firm, with a maximum bid price of $200/MWh.
  • PJM sets no uniform price trigger. It proposes firm and non-firm contract demand plus an interim, energy-only service, and the Fast Energization Process that studies loads and generation together in about 12 months.
  • CAISO proposes a Flexible Interim Load Interconnection, with operating limits set project by project, such as preset schedules or automated remedial action schemes, so a load can be energized before network upgrades are complete.

None of this is in force. FERC still has to rule, and several operators expect detailed tariff work and start dates in 2027 or later.

Non-firm means the generators have a job

A load that accepts interruption at $100 or $250 a megawatt-hour has to decide what happens in the hall when the signal comes. Either the IT load is reduced, or something on site carries it. If that something is the standby fleet, the plant is no longer only emergency plant, and the air permit, which for emergency engines limits the hours they may run outside a real outage, becomes the first document to check. We raised the same point when a former FERC chair warned that backup diesel was drifting into routine use.

The price triggers also say something about how often. One percent of hours in New England is a very different duty from a MISO curtailment that comes with every capacity advisory. Fuel stock, refuelling contracts, maintenance intervals and noise at night all follow from that number. PJM's separate ride-through filing adds the other half of the question: when the grid disturbs the load, it does not want the load to leave at once.

Sources: POWER, American Public Power Association