PJM Wants Data Centers to Ride Through Faults, Not Jump to Gensets

On 22 July a routine disturbance on the transmission system in the Dominion zone made nearly 3.9 GW of data centers leave utility supply and move onto their own onsite generators. PJM calls it the largest load transfer of its kind in its history. On Monday, 16 November, the grid operator asked FERC for rules to stop it happening again: large computational loads would have to ride through voltage and frequency disturbances instead of disconnecting.

A 50 MW threshold and a January date

According to PJM's own news service, the proposal creates a new category, the Large Computational Load (LCL), for any load of 50 MW or more. PJM says the threshold matches the standards FERC and NERC are developing and the approach of other grid operators. The ride-through requirements would take effect on 16 January 2027 for existing and new sites alike:

  • a new LCL has to show compliance as a condition of interconnection and operation;
  • an existing LCL gets one year from the effective date, or one year from commercial operation if that comes later.

PJM serves about 10 GW of such load today and forecasts up to 30 GW more by 2030. It says the July event affected voltages, frequency, power flows and generator behaviour in the Dominion zone and across the Eastern Interconnection. The control room managed it, but PJM describes the size and speed of the transfer as a serious threat to reliability and safety. EnerKnol adds that the Dominion zone had seen unexpected transfers of about 1,500 MW twice before, in July 2024 and February 2025. Ramp rates and other performance requirements are left for further work with stakeholders. None of the published summaries gives the voltage or frequency limits themselves; those sit in the filing.

The same day PJM filed its answer to FERC's June show-cause orders on large loads. Utility Dive reports that the centrepiece, the Fast Energization Process, would study large loads and generation together in a single review of about one year, which PJM says is roughly twice as fast as today. PJM's transmission owners filed separate tariffs for serving large and co-located loads.

Why the gensets started on 22 July

A data center that sees a voltage dip does what its designers asked of it: it protects the IT load, rides on the UPS and starts the generators. When dozens of sites on the same part of the network do that at once, the grid loses gigawatts of load in seconds, and that is the half of the story the grid operator sees. Statnett in Norway paused new data centre grid reservations over the same kind of question.

For the people who look after the standby plant, the rule moves a decision point. Transfer settings at the site boundary are normally chosen to protect the building. Under a ride-through requirement they also have to keep the site on the grid through disturbances it used to treat as a reason to leave. That is a conversation between the electrical designer, the UPS supplier and whoever commissions the generator controls, and it is better held before January than after the first compliance review.

One side effect is easy to overlook. A site that rides through instead of transferring also logs fewer unplanned generator starts, and that counts wherever the air permit limits operating hours.

Sources: PJM Inside Lines, EnerKnol, Utility Dive