Ten tons a year is the line. Under the Ohio Administrative Code, a source that is expected to emit more than that of volatile organic compounds, coarse or fine particulate matter or sulfur dioxide has to use best available technology, BAT for short. The draft air permit for the Fairfield Energy Center, a 1,350 MW power plant for a data center near Millersport, puts each of the plant's 40 turbines and diesel engines below the line and so exempts each of them, and Ohio EPA staff recommend approval. That is how The Reporting Project, the news service of Denison University's journalism program, reads the document. The public hearing was held on Tuesday, 10 November, at Millersport Elementary School, and comments could be filed online until 12 November.
What is planned off Route 204
The developer is Advanced Power Services of Boston. The plant would stand on 450 acres owned by Vantage Data Centers along Route 204 just west of Millersport in Fairfield County, where Vantage proposes a hyperscale data center for $2.1 billion. The Reporting Project describes the equipment as 40 simple-cycle turbines and reciprocating diesel engines, without giving the split between the two, and says the plant would be among the largest built for a data center in Ohio so far.
From the company's applications the report takes these yearly emissions for the whole facility:
- carbon monoxide: 686 tons
- nitrogen oxides: 486 tons
- particulate matter: 333 tons of PM10 and 333 tons of PM2.5
- volatile organic compounds: 221 tons
- sulfur dioxide: 86 tons, and sulfuric acid mist: 19 tons
Greenhouse gases are given as 7,232,826 tons, a figure the Ohio EPA documents mark as not applicable to the permit.
One facility or forty units
Cathy Cowan Becker, president of the group Save Ohio Parks, says the agency is stretching its rules. Her argument is that the permit is issued for the facility and not for a single engine, so the facility's totals should decide whether BAT applies. She also holds that a simple-cycle design is not the best technology available. The report adds that the combined-cycle turbines Advanced Power has run at its plant in Carroll County since 2017 are in such demand that manufacturers cannot keep up.
Ohio EPA sees no conflict. Press secretary Bryant Somerville wrote that the Fairfield Energy Center is a major emitting facility and has to use BAT under state and federal rules. Smaller units with emissions under 10 tons a year are not significant and may be exempt under Ohio Revised Code 3704.03, he said. Some units at the plant were found to be exempt, other state and federal emission limits still apply to them, and the agency handles every air permit in the state the same way.
The project is also before the Ohio Power Siting Board, as case 26-0160-EL-BGN. Around New Albany, where residents are worried about fine particulate matter, seven gas-fired plants are proposed for the International Business Park: one is running, four are under construction and two are before the board.
Why the count matters to the supplier
Whether a fleet is judged unit by unit or as one source is not a lawyer's detail. It decides whether exhaust aftertreatment goes into the specification because the permit demands it, or stays out because every engine slips under a threshold on its own. The fleets are large enough by now for the answer to matter: in West Virginia one air permit under review covers more than 800 engines on a single campus.
If a permit like this one is challenged and comes back with limits for the whole site, the equipment is usually already ordered. Adding a reactor, a reagent tank and the piping to an engine package that was laid out without them is a different job from designing them in. A buyer who expects the argument would do well to leave the space and the connections for it on day one.
Sources: The Reporting Project