JLL: Labor Shortages Put US Data Center Schedules at Risk

A data center can be substantially complete, with power available, and still be months away from operation because nobody is free to commission it. Matthew Giddings, executive director of technical services at JLL, gave that example in a Data Center Knowledge report of 13 November on the firm's 2027 US Construction Perspective. The report's message is that labor, more than money, is making schedules fragile, above all in the southern states where specialist crews are already stretched.

Prices first

JLL forecasts that national tender prices, the prices contractors bid, will rise 4.2% in 2027, after 3.1% in 2026. Before 2020 the usual range was 2% to 3%. The forecast covers the construction market as a whole, not only data centers. Tender prices tend to follow input costs with a delay of three to six months, so what metals and energy-intensive products cost at the end of 2026 will show up in bids early in 2027.

The South is expected to contribute more to non-residential construction growth than any other US region and, by 2028, to carry the heaviest workload per worker. Data centers, power projects and public civil works are the drivers.

More crews do not fix everything

According to the report, developers are already paying overtime and covering travel, lodging and relocation premiums to assemble crews, and Giddings warns that the cost of qualified crews is easy to underestimate. Adding people can raise the cost without raising output when design, materials and sequencing are not coordinated. Emerging markets may not have the workforce for several hyperscale projects at once, because a campus now includes substations, utility infrastructure and dedicated generation, and needs thousands of workers over several years.

Two more points from the article:

  • Utility transmission and substation crews and a developer's electrical trades are not interchangeable.
  • Prefabricated electrical assemblies and standard cooling reduce site labor, but the factories that build them have staffing limits of their own. Giddings sees more value in designs repeated across campuses than in isolated prefab choices.

His conclusion: overtime and extra people achieve nothing if the real constraint is transformer delivery, utility energization or commissioning. Acceleration money should go to the actual bottleneck.

Where the genset sits in this

On the backup power side, commissioning is exactly the step that gets squeezed. The generators arrive late in the programme, the engine maker's service engineer is booked on three sites, the load bank and the fuel for the tests have to be on site on the same days, and the integrated test with the switchgear depends on another trade being finished. None of it can be bought back with overtime at the end. The commissioning team and the test dates belong in the order, not in the last month of the schedule.

Sources: Data Center Knowledge