Fort Worth Panel Wants 350-Foot Generator Setback for Data Centers

Standby generators sit a long way from where Fort Worth's data center debate started, but they run through half of the answer. On 10 November the city's Data Center & Infrastructure Commission, chaired by Michael Slattery of the Institute for Environmental Studies at Texas Christian University, handed the City Council its final report: 156 pages and 19 recommendations on electricity, water, land use and the local economy. The commission was set up by council resolution in August and only studies; it decides nothing.

The same evening the council held the first of two public hearings on a possible 90-day pause on new data center development. CBS Texas reports that dozens of residents spoke, that the second hearing is tentatively set for 12 January and that a vote could follow in February.

Generators move back from the fence

City staff had proposed in June that standby generators stay 300 feet from residential property. The commission wants that replaced by what it calls a Neighbor Protection Distance of at least 350 feet from homes and other sensitive uses, longer for taller buildings. It also backs the staff proposals to fully screen the generators, to put rooftop cooling plant behind an acoustic barrier and to plant a buffer strip along residential boundaries. The report is open about it: these distances are policy choices, not values derived from research.

On noise the commission goes further than a single limit. Its framework asks for background monitoring before construction, a predictive model of the full build-out that includes generator tests, and a survey of the finished plant before it is allowed to run freely. Readings would cover C-weighted levels and one-third-octave spectra as well as the usual A-weighted figure, because hum from fans and transformers is easy to miss otherwise. A low-frequency pilot study at existing data centers should start within six months of council action and report back by June 2027. Testing hours, the report notes, can be limited through the noise ordinance.

What the city cannot touch

Air permits are not the city's business. In Texas the Commission on Environmental Quality (TCEQ) licenses backup generators, and a municipal rule may not be stricter than what TCEQ has authorised. So the commission asks for a plain guide to finding generator permit records on TCEQ's website and for the 2050 Comprehensive Plan to address the air quality effect of clustered backup generation.

The findings behind that are worth reading for anyone who permits generator fleets in Texas:

  • Tarrant County is in ozone nonattainment, and the major-source threshold for NOx in the Dallas-Fort Worth region has been cut twice in three years, from 100 to 25 tons a year. A fleet that was a minor source before may not be one now.
  • Operating hours must be logged, but there is no public record of actual test, emergency or dispatch hours.
  • None of the sources reviewed looked at several campuses running their generators at the same time during one grid event.

The city lists four existing data center developments with about 3 million square feet, two under construction and several proposed, the largest of them, Black Mountain in south Fort Worth, at an estimated 980 MW.

For a project team the useful part is the order of work. If these proposals pass, the generator yard position, the screening and the acoustic model are settled before approval, and a post-construction survey decides when the plant may run without restriction. Generator test runs end up in the noise study whether anyone planned for it or not. San Jose is writing its own standards at the same time, see Google's 250 MW project there.

Sources: Fort Worth Data Center & Infrastructure Commission, Final Report, CBS Texas