Riot Leases Its 910 MW Corsicana Campus to an AI Lab for 15 Years

Riot Platforms built its Corsicana site to mine bitcoin. Now it is renting all of it to an AI developer. With its third-quarter results on 4 November, the company announced a 15-year triple-net powered-land lease with what it calls a leading frontier AI lab, covering 910 MW of critical IT load on a contiguous 332-acre parcel. Riot did not name the tenant; Texas Construction Hub, which places the site in Navarro County, Texas, reports that it is Anthropic.

Who builds what on the pads

The split of work is the part worth reading twice. Riot provides the land, the power infrastructure and finished powered pads, and it keeps owning and maintaining the high- and medium-voltage equipment. The tenant buys, installs, owns and operates modular compute on those pads and carries substantially all operating costs, with the utility bill passed through; on the earnings call Riot said it adds no markup. Rent is due on the full 910 MW whether the capacity is used or not, and each phase starts paying no later than 60 days after its pads are handed over.

Riot puts the contract value at about $28 billion over the initial term, roughly $1.8 billion a year on average including escalators, and at about $54 billion if both five-year extension options are exercised. Capital comes to about $6 million per IT MW, or $5.5 billion in total. Riot pays about $2 million per MW for site work and electrical infrastructure. The other $4 million per MW is spent by the tenant and reimbursed by Riot in stages once each phase is delivered and paying rent, and Riot plans to fund its share with non-recourse project debt sized to the rent.

Three phases in under two years

  • 400 MW in September 2027
  • 200 MW in January 2028
  • 310 MW in July 2028

On the call, chief executive Jason Les said the 910 MW comes out of the same 1 GW of utility load already approved for the site; the original Tier 3 design basis had allowed for up to 756 IT MW. Bitcoin mining can carry on through the first phase but has to come down before the second, which Riot expects around the summer of 2027. Together with a 191 MW lease at Rockdale, which Riot says is with the same lab, and its 50 MW contract with AMD, the company now has 1,151 MW of contracted data center capacity. For the quarter Riot reported revenue of $181.4 million, up 1%, and net income of about $4 million.

Les called it the largest lease in Riot's history. Neither the release nor the call says who will provide standby power for the compute, and under this structure that is something to watch: the pads come with grid power, everything above them belongs to the tenant. Whoever ends up with the job has to order, permit and commission standby plant for a first phase of 400 MW due in September 2027, about ten months from now, on a site that has so far been run as a flexible mining load that could simply switch off. The fuel storage and the load bank tests for the first phase will need a place in that schedule from day one.

Sources: Riot Platforms (via StockTitan), The Motley Fool (call transcript), GuruFocus (via Yahoo Finance), Texas Construction Hub

Other News